Permit Requirements for New Construction in Frederick County, Maryland
*Taken from official Frederick County Permitting Services
The permitting process can be somewhat intimidating.
|
|
Approval Requirements
Approval is required for all new construction in the county or in the municipalities, with the exception of the City of Frederick and Mt. Airy. The City of Frederick and Mt. Airy are responsible for their own building permits. Zoning certificates for properties within municipalities must be applied for prior to Building Permit application at the Department of Permits and Inspections. Approval is required for modifications, alterations or changing the usage of any building or structure. Approval is required for accessory structures, such as a shed, pool, deck, garage, sign, etc.
For non-residential, commercial construction projects, plans are required to be signed and sealed by a licensed Maryland architect or engineer. 3 sets of plans are required for submittal. 1 set is retained by the Department of Permits and Inspection, the Office of Life Safety retains another, and 1 set is returned to the applicant with comments.
Permit requirements in Frederick County, Md.
When is an Electrical Permit required in Frederick County, Maryland
Electrical permits are required to provide safeguards for person and property from the risk of hazards arising from the use of electricity. Any time that electrical work is to be done, an electrical permit is required. If the work is being performed in connection with a Building Permit, then the Electrical Permit is not approved until after the Building Permit is approved.
Approval is required for all new construction in the county or in the municipalities, with the exception of the City of Frederick and Mt. Airy. The City of Frederick and Mt. Airy are responsible for their own building permits. Zoning certificates for properties within municipalities must be applied for prior to Building Permit application at the Department of Permits and Inspections. Approval is required for modifications, alterations or changing the usage of any building or structure. Approval is required for accessory structures, such as a shed, pool, deck, garage, sign, etc.
For non-residential, commercial construction projects, plans are required to be signed and sealed by a licensed Maryland architect or engineer. 3 sets of plans are required for submittal. 1 set is retained by the Department of Permits and Inspection, the Office of Life Safety retains another, and 1 set is returned to the applicant with comments.
Permit requirements in Frederick County, Md.
When is an Electrical Permit required in Frederick County, Maryland
Electrical permits are required to provide safeguards for person and property from the risk of hazards arising from the use of electricity. Any time that electrical work is to be done, an electrical permit is required. If the work is being performed in connection with a Building Permit, then the Electrical Permit is not approved until after the Building Permit is approved.
Permit Requirements
Plumbing permits are required to provide practical plumbing regulations for the safeguarding of person and property from hazards arising from unsanitary and unhealthy plumbing conditions. Any time that plumbing work is to be done, a plumbing permit is required. If the work is being performed in connection with a Building Permit, then the Plumbing Permit is not approved until after the Building Permit is approved.
Approving Agencies: Department of Permits and Inspections
Processing Time: Plumbing permits are usually issued within a time frame of 1 to 2 days from the day the application is made and the fee is paid. Applications are required to the department before the plumbing work is started.
Duration of Approval: Plumbing permits are valid for 1 year.
Application Process
Building permits are required to establish minimum requirements for the protection of life or limb, health and public welfare and protection of property as it relates to the structures built or existing structures being modified or altered. Application is made at the:
Department of Permits and Inspections
30 N. Market Street
Frederick, MD 21701
Applications must be made in person between the hours of 8 a.m. - 3:30 p.m., Monday - Friday, excluding holidays. For further information, please select a specific certificate or permit type below.
Plumbing permits are required to provide practical plumbing regulations for the safeguarding of person and property from hazards arising from unsanitary and unhealthy plumbing conditions. Any time that plumbing work is to be done, a plumbing permit is required. If the work is being performed in connection with a Building Permit, then the Plumbing Permit is not approved until after the Building Permit is approved.
Approving Agencies: Department of Permits and Inspections
Processing Time: Plumbing permits are usually issued within a time frame of 1 to 2 days from the day the application is made and the fee is paid. Applications are required to the department before the plumbing work is started.
Duration of Approval: Plumbing permits are valid for 1 year.
Application Process
Building permits are required to establish minimum requirements for the protection of life or limb, health and public welfare and protection of property as it relates to the structures built or existing structures being modified or altered. Application is made at the:
Department of Permits and Inspections
30 N. Market Street
Frederick, MD 21701
Applications must be made in person between the hours of 8 a.m. - 3:30 p.m., Monday - Friday, excluding holidays. For further information, please select a specific certificate or permit type below.